19D Update Account and Budget Date on Budgetary-Controlled Open Purchase Orders
Content
We are testing out the changes for the 19D upgrade and trying to confirm what specifically this change is supposed to make. We've been able to make changes to the line or distributions prior to this, so we're not exactly sure what we're looking at. The functional users and I have tested and don't find any visible difference or option. I'm including the description and link below. Thanks!
Jon
Upgrade notes:
Change account and budget date on open purchase orders, even if subject to budgetary control. You can make the changes if there are no project references on the purchase order distributions. The necessary funds checks and adjustments to funds reservations and encumbrance accounting when applicable are handled based on the updated information. This is done by automatically liquidating funds reserved against the old account and budget date, and reserving funds to the new account and budget date.