PTF Behavior ask for details
Summary
PTF Behavior ask for detailsContent
Hi Team,
if Planning time fence days = Null and Planning time fence type = Null, and Planning time fence control checkbox is checked. Will system still show Planning time fence date even if we have Post Processing lead time in it for Buy Items? If yes, then why system is using PPLT days as Hard Constrained even if we are using Uncontrained Plan?
Can anyone please suggest anyway out for system to not consider PPLT when PTF days and type is null? any workaround available? why is it behaving like constrained supply plan?
Thanks