When scheduling jobs in OIC, there is no option to create dependencies between jobs.Content
When scheduling jobs in OIC, there is no option to create dependencies (ie) job B should run only when job A is completed.
We can currently schedule jobs to run at various times, but job B does not wait till job A finishes.
We have a situation where we are deleting and reloading a table (job A), during which time the other jobs (for example job looking for this data should not run. Since we cant define a dependency between job a & job B, we are looking at the average duration of Job A and adding 15 minutes to schedule job B. This is not an efficient method. If job A overruns the duration we have defined, then job B fails as data is not available.