You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register

Reverse a Committed Cost in Project from a Requisition that was never completed

edited Jul 26, 2021 9:50PM in Project Management 3 comments

Content

I understand from this post https://cloudcustomerconnect.oracle.com/posts/11d529edc6  that 1. Once a requisition is raised it is reflected under Committed Cost.

However we had a Requisition raised that was never submitted for approval and stayed in Incomplete status (did not become a PO and actually sent to a supplier).  But it did come over to Projects when we imported costs. 

We have deleted the requisition in the Procurement module. 

How do we get the committed cost out of the Project as it's skewing the project cost?  

I found this post:  https://cloudcustomerconnect.oracle.com/posts/7b8219015a

Tagged:

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!