Project Performance - Does not show Baselined Cost Budget
I created a new Project and FInancial Plan, periodic by named resource. I have successfully baselined a budget and updated project performance, but the budget information does not show up in Review Project Performance, all my values are $0. What may be the cause? Thanks in advance.
It's quite possible it is because I did not mark the Financial Plan as an Approved Cost Budget plan, where am I able to include this plan into summarization? The following advises it can be done, but not sure where.
https://docs.oracle.com/en/cloud/saas/project-management/22a/oapfm/Chunk1175175641.html
Esmeralda