Shared MFG RES:How to split planned order for two items equally or in proportion to their demand?

edited Aug 2, 2022 1:14AM in Supply Chain Planning and Collaboration 2 comments

Summary:

Shared MFG Resource in a Constrained Plan: How to split planned order between two items equally or in proportion to their demand?

Content (required):

Scenario:

We have two assembled items A & B that use the same MFG resource in their work definition. Demand for both items is loaded via External Forecast. Let's say the daily MFG production capacity is 2000 units. The daily demand for both items is 1200 and 1500 units. I am not planning to define alternate work definitions and resources.

Expected Behaviour:

I need the system to either

  1. Split production equally between A & B i.e. 1000 units each or