Does Supply Planning in Constrained Mode support Pre and Post Processing Lead times for Make Items?
Summary:
I am testing via Simulation sets and I do not see Pre and Post processing lead times impacting the dates on the planned orders. Does Supply Planning in Constrained Mode support Pre and Post Processing Lead times for Make Items?
Content (required):
I have defined Pre, Post, and Processing lead times for a Make item which is added to a simulation set. Next, I created a manual demand for this item and ran the plan w/o data refresh. For the planned order, I see suggested start and ship dates are equal which means no impact on preprocessing lead time. Further Suggested Dock Date is equal to Suggested Due date which means the post-processing lead time is not taking effect as well.