Supplier capacity Constraint not getting enforced in Plan
Summary:
Supplier capacity Constraint not getting enforced in constraint supply Plan
Content (required):
We have defined a constraint Plan and enforced the supplier capacity constraint. We have made Enforce purchasing lead time as No for all buy items in the Item Structure. The supplier capacity is defined for suppliers and items are linked to supplier via ASL, sourcing rules are in place. No alternate sourcing provided or item substitution defined.
The Plan output is not enforcing the supplier capacity and still enforcing demand date. we are also getting exception of Supplier capacity overload.
Here supplier capacity defined is 2 pc per day and demand is 200 pcs, plan start date is 27-09-2022 and SO requested date is 13-Oct-2022.