SCP: Safety stock based on baseline forecast only
Summary:
We have 2 forecasts - Baseline forecast and Promotional forecast and would like Safety Stock to be calculated using the Baseline forecast ONLY.
Can this be achieved and if so how?
Attachment Fusion_R13__Managing_Safety_Stock_with_Supply_Planning_1.pdf in Managing Safety Stock with Oracle Supply Planning Cloud ( Doc ID 2226042.1 ) states the following. Does this mean there is NO way to have the Safety Stock calculation using the Baseline forecast ONLY?
Demand Schedules
To calculate safety stock, planning considers the demand schedules attached in the Organizations and Schedules tab. If the same item-organization combination is present in multiple demand schedules, planning engine calculates a separate safety stock value for each demand schedule and then sets the safety stock for the item as the sum of the safety stock values calculated from each demand schedule.