PPM Cost Allocations -Prorate method logic
Summary: PPM Cost Allocations -Prorate method logic
Content (required):
Hi Team,
I would like to Understand the Logic of Prorate basis method of calcuating the allocation costs.
Source pool amount is 15,300
Target Allocated amount for SK_01 Project is 1597. 32 ; and another Project SK_02 is 2.68.
Im trying to understand the logic defined in Oracle Document. But im not able to connect the logic.
Could you please help in understand how the allocation calculates in case of Prorate basis method.
Formula for Prorate.
( target task basis amount / total basis amount ) * source pool amount = allocation amount
( target task basis amount / total basis amount ) * 100 = basis percentage