The availability of resource must be 24X7, although the calendar is designed for 5 days each week
Summary:
Resource is enabled for 24 hours but it follows the calendar defined which is 5 days each week. On these 5 days of the calendar the resource is 24 hours available. But on other 2 days manufacturing is not considering for start & completion date of the operation.
Content :
We have a requirement where the resource of 2nd operation of the work definition must be working 24X7. When the work order is released manufacturing cloud doesn't consider the Saturday & Sunday for start & completion date of the operation (In planning it does consider).Even though the resource is enabled for 24 hours it still follows the calendar and is available as 24X5. Business wants manufacturing to consider these 2 days (Sat & Sun) and show the start & completion date.