Planning Functional Area Catalog is master controlled but Planning Method attribute is org controlle
Summary:
Initial configurations done were as follows -
MPS and MRP Planning, Planning Method = Master Controlled
Planning Functional Area Catalog = Master Controlled
Then,
We updated the MPS and MRP Planning, Planning Method to be organization level controlled.
As per the documentation, if Planning method is org controlled, then planning functional area catalog will be org controlled as well.
This is working fine for now.
But is this a bug in the system? Will there be any issues down the line?
Content (required):
Version (include the version you are using, if applicable): 22D
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged: