Forecast revenue error encountered on a project with amount based lump sum contract, is it expected?
Summary:
We have a scenario where a Lump Sum project with an amount based bill plan on the associated contract is encountering an error upon forecast generation.
Error encountered is: A revenue rate or markup percentage wasn't found for the planning transaction using the resource class bill rate schedule.
Content (required):
We did not configured the Resource Class Bill Rates to have any rates and this is a global configuration.
In addition, upon creation of the forecast, error is not encountered but when users ran the refresh rates, the error started to pop up.
Version (include the version you are using, if applicable):
0