Project Cost Balance Discrepancy due to exchange rate
Summary:
Unable to raise a Purchase Request due to Project Cost Balance Discrepancy due to exchange rate
Content (required):
Project Budget : 40,000 SGD
Project Balance : 5,551.52 SGD (due to exchange rate difference on Project Expenditure Date and Receipt date, the balance should be 8,898.36 SGD)
Unable to raise a Purchase Request of 6,000 SGD. Refer to the below on the transaction details:
Project PO Line Item Details:
Amount : 21,981.30 EUR
Project Expenditure Date : 26 Nov 21
Exchange Rate : 1.567
Converted Amount to SGD : 34, 448.48 (capture as Project Expenditure)
Project PO Receipt Details
Amount : 21,981.30 EUR
Receipt Date : 14 Dec 22
Exchange Rate : 1.415
Converted Amount to SGD : 31,101.64 (capture as Receipt Expenditure)
For the same line item, due to the exchange rate different (3,346.84 SGD), how can we release the exchange rate different back to the project budget?