In supply planning can a planned order be release to be a rework work order?
Summary:
Scenario:
Client receives a huge assembly for rework, the disassemble it some components again needs the rework, there are like 8 levels of BOM where each component needs a rework
So client creates a rework work order for Assembly manually and Planning collects that rework work order and explodes it
But in explosion planned orders are created for components and when released it created a standard work order, but we want is the when assembly rework work order explodes it should create planned order which when released will create a rework work order as per the rework work definition, if we use standard work definition then inventory increases that's what we don't want.