is there a link between labor resources in PEM and request resource?
Summary:
is there a link between labor resources in PEM and request resource?
We are adding labor resource in Project management on task level . The allocation of this resource will be 100 % by default so we will have the effort by hour
Is there a way to limit the resource request assignment when requested by Project manager or by the resource pool manager ? i.e. Here we have 80 hour , so is there a way to limit the resource request to maximum 80 hours?
Content (please ensure you mask any confidential information):
Version (include the version you are using, if applicable):
23C
Code Snippet (add any code snippets that support your topic, if applicable):