Physical percentage Complete Calculation are not getting calculated as expected on a project.
Summary:
Physical percentage Complete Calculation are not getting calculated as expected on a project.
Content (please ensure you mask any confidential information):
Hi Team,
Im trying to capture progress on a project, Physical percentage is not getting calculated correctly and even not rolling up to the Top Task.
Physical Percentage complete method on Project Plan type is "Cost"
Steps followed :
- Created Project and tasks , baselined the project.
- Created Budget and base lined.
- Created Forecast and approved.
- Created Costs and accounted.
- Now, Open Project, navigated to manage Financial Project Plan , Progress Tab.> Click on Capture Progress. ( this point where the progress is not getting calculated and rolling up to the top task)