Resource does not consider LT in supply planning
Summary:
We have an item that will take 14 days to manufacture (process LT is 14 days).
Looking at the resource requirement in the resource plan, the plan is to start manufacturing on 6/16 and complete some quantities on 6/23.
Why does the plan ignore LT in this way?
How can we make a plan that takes LT into account?
Content (please ensure you mask any confidential information):
■Resource Plan
When drill to the blue area↓
■Supplies and Demands
Version (include the version you are using, if applicable):
Code Snippet (add any code snippets that support your topic, if applicable):