FBDI Upload - Project Budget set to baseline loads as current working for $0 budget load
Hello!
I need to create an original baseline with a $0 budget for a project with budgetary controls enabled. When using the FBDI import project budget process I see on the Project budget that is does not set it as original baseline or create a control budget.
When I load for a $0.01 project budget it creates the project baseline and the control budget. Why is this and is there a configuration setting I can update to allow the $0 original baseline amount?
Thanks!