Question on KPI Setting for Project Management Infolet [Health]
Summary:
Hello Oracle Community,
User wanted to use the Project Management Infolet which is [Health].
As we understand these Project Health are based on KPI thresholds.
We have a below requirement from the user for their KPI in Project management.
The following are assumed as Critical conditions when setting up the KPI.
- The contractual start date has passed and a budget has not been created.
- The contractual start date has passed and the order rate is below 80%.
- The contractual start date is next month and the order rate is below 60%.
- The construction profit is negative/low
Is it possible to set the KPI with these conditions? Or there certain parameters only when setting up the KPI?