Plan suggested sequence should based on shortest change over time.
Summary:Plan suggested sequence should based on shortest change over time.
Example - Product A cannot be produced immediately after product B whereas product B can be produced immediately after product A.
Product B to Product A change Over time - 1 hr.
Product A to Product B change Over time - 0 hr.
Plan suggested sequence should be based on shortest change over time i.e. to produce product A first and then product B.
Similar behavior in case of allergen, plan should suggest producing generic product first and then allergen