Ability to burden one expenditure type at multiple burden rates?
Example: $1,000 worth of labor - comes in from OTL with Salaries Expenditure Type
Burden Rates:
1x - Cost Code A
2x - Cost Code B
3x - Cost Code C
PPM Burdening needs to burden as the following:
1,000x1=1,000
1,000x2=2,000
1,000x3=3,000
total of 6,000 for the JE in burden cost
Currently I believe there is only a one to one relationship between expenditure type and burden cost code, even if you put two codes on the same expenditure type it only looks at one.
Any way to take into account multiple burden rates/cost codes if the expenditure type is not called out on the OTL side?
Tagged:
0