Hi Team,

We have a requirement to configure the Project Budget Approval workflow in BPM

  1. Initially we have configured the Project Budget approval workflow in BPM, its working fine ( as per BPM configurations).
  2. And, we want to create another project budget version (ex.version2) and submit, then it will go another workflow.

Requirement:

Initially we have configured the Project Budget approval workflow in BPM based on Project Roles and Approval Groups. now, we want to configure second level approvals ( if the Project Budget submit second time based on current baseline, it will trigger the new workflow)

Please let me know, How to configure the Project Budget workflow with different requirement (version 2) if the project have the baselined budget (based on the approval Project Budget version1 approved)