Need-by Date
We are on 11.5.10.2
We use minmax to generate requistions for purchased items. We have, for example, a 7-day lead time on the item. However, our supplier only ships one day per week. As a result, lead times must be long enough to cover the non-ship days. In most cases the shipment actually arrives sooner that the need-by date.
Is there any way to set the need by date dynamically (for atp purposes) based on the one day per week shipment? For example, set need-by date to next available ship date + transit time.
Any help would be greatly appreciated
Thanks