differences bt BL budget & act. for past periods when converting and assigning current project as ba

edited Jan 29, 2014 2:37PM in Primavera (MOSC) 2 commentsAnswered
 Dear Experts,

Kindly check below Issue and let me know your idea/solution about that: 

Problem description: 
1-  I converted the current project as baseline and assign it to the project.
2- in the administration Earned value setting I choose either of one of the options "Planned Value with current date" or " At completion values with current dates" 
3- I expect that the baseline schedule bars to be same as the current schedules bars which is correct no problem on that. 
4- I also expect that past period actual and BL Budget be the same (before data date) and the balance budgeted values (or units) to transfer to remaining period of each activities

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center