ePro Req has 2 different vendors, so 2 PO's are created. PO line_Nbr increments by the Req, instead

edited Oct 21, 2016 12:53PM in Supply Chain Management - PSFT (MOSC) 8 commentsAnswered ✓

Fortunately this issue only happens in the test environment. Not in prod.

To test:

- create one ePro requisition with multiple lines, and more than 1 vendor.

- run the budget check, auto source req, po calculate, po create processes.

- look in ps_PO_LN_DISTRIB for that req_id and see what the PO line_nbr's are.

Should be:  po123 line 1, po123 line 2, po124 line 1, po124 line 2

Notice the PO line numbers are reset back to 1 when a new PO is assigned.

However in test environments, I'm getting this:

po123 line 1, po123 line 2, po124 line 3, po124 line 4.

This must be some kind of flag or setup that I'm missing.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center