Assigning more than 2 CBS codes on the activity in Activity Sheet
Hi,
This is an enhancement request regarding subjected issue.
Please see the below my SR for the issue.
Now, Unifier allows creating manual activity sheet in version 20.12.
but it's just invented for schedule management only without cost management.
This is because each activity in manual activity sheet has only one CBS code.
So, my questions are:
1. Is there the way to assign more than 2 CBS code in activity?
2. Without integration with EPPM, how to allocate BAC, PV, AC, ETC and etc on the Activity? (these elements are system pre-defined and read-only that user cannot modify)
3. If 2. is possible, how to allocate activities' budget into WBS Sheet?