Oracle PS: Setting Maximum Weekly Production Quantities per Item on a Resource
Hi everyone,
We are currently implementing Oracle Production Scheduling and have a question regarding capacity planning and production limitations for shared resources.
Scenario:
We have a single machine (resource) that is used to produce multiple items (let's say 5 different models). We have already set up the standard routings and operations in Oracle EBS, which define the hours required to produce each item on this machine.
The challenge we are facing is capacity planning. We know that the total demand for all 5 models will likely exceed the machine's available weekly capacity. To manage this and ensure a balanced production mix, we need to enforce a business rule that limits how much of each