Automatic Forecast consumption

Comments

  • johnboyack
    johnboyack Posts: 215 Bronze Badge
    Hello, and thank you for this document.  We need to solve a very similar scenario here because of long manufacturing and purchasing lead times.  We use OPM (Oracle Process Manufacturing) not BOM.  I am told that before I arrived at this company "product family" was tested and did not solve the scenario as it does for discrete.

    I am now performing research from scratch.  Do you have any suggestions to resolve this in an OPM instance?

  • User584854-OC
    User584854-OC Posts: 63 Blue Ribbon
    Hello, and thank you for this document.  We need to solve a very similar scenario here because of long manufacturing and purchasing lead times.  We use OPM (Oracle Process Manufacturing) not BOM.  I am told that before I arrived at this company "product family" was tested and did not solve the scenario as it does for discrete.

    I am now performing research from scratch.  Do you have any suggestions to resolve this in an OPM instance?

    HI

    just have question you made forecast on 25-may-2011 as sales order are present 

    but purchase lead time is 300 days so when we will receive material and how you will full fill sales order on 25 feb 2011

    please throw light on procurement process also