Process Manufacturing - EBS (MOSC)

MOSC Banner

Batch_material_transaction_problem.docx

user13619436
user13619436 Posts: 2 Newbie
edited Oct 18, 2016 8:08AM in Process Manufacturing - EBS (MOSC) 2 comments

Comments

  • CaioMSMancini
    CaioMSMancini Posts: 499 Gold Badge

    Hi.

    Did you log a SR in order to get this checked?

    It might be a bug.

  • Bala Alwar
    Bala Alwar Posts: 921 Bronze Trophy
    edited Oct 18, 2016 5:22PM

    Hi,

    It is not a bug.

    If you want to yield pending lot in two different sub-inventories, do transact material twice for the Product(s).

    Also, Allocated Qty (Pending Lot Qty) doesn't have significant value in the Batch Details form. Once Batch is Completed, Pending lot & qty would be cleared and no longer available for further transactions. Material Exception form also show up as '0' for products, where Actual Qty is equal to WIP Plan Qty.

    To yield product(s) in Fill SubInv;

    Batch Details >> Select Product >> Transact Material

    Check 'Transact' box > enter FILL SubInv > enter Locator > Change (Actual) quantity > Transact

    For FG SubInv, Again,

    Select Product >> Transact Material

    Check 'Transact' box > enter FG SubInv > enter Locator > Change (Actual) quantity / Remaining Qty > Transact

    Now, you can see that pending lot qty decremented by these transactions.

    It is because, you created only one sequence (100) in pending lot form. So that, the first line qty only decreased by transaction.

    -Bala