Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Update your Profile with your Support type to get your Support Type badge.
Uncover the power of data with the Analytics Hub —your ultimate guide to mastering NetSuite Saved Searches and Reports. Simplify the complex and unlock your organization's true potential. Dive into the Analytics Hub now and soar to new heights!
To help you get the most out of your 2025.2 Release Preview account, review the topics outlined in the 2025.2 Release Preview Guide.
Nominate Your Peers for NetSuite Support Community's Choice of the Quarter! Submit your nomination today.
Intelligent Payment Automation version 1.0.3 is now available in the SuiteApp Marketplace. The SuiteApp, powered by BILL, lets you automate payments, manage vendor details, and bank account information within NetSuite. Learn more
MRP and WO Production End Date
I have a work order that was manually created. I am using Forward scheduling. The "Production End Date" that NS is calculating is not what I want to use as the end date due to staggering scheduling.
I updated the Actual Production End date to be align with current MFG Schedule.
When MRP was run, NS is appears to be looking at the "Production End Date" that is locked down and calculated based on the routing.
the action is to delete the WO and issue a new won in ordinance with the Production End Date.
Does MRP ONLY look at the Production End Date that is calculated based on forward or backward scheduling?