Discussions

Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Update your Profile with your Support type to get your Support Type badge.
Uncover the power of data with the Analytics Hub —your ultimate guide to mastering NetSuite Saved Searches and Reports. Simplify the complex and unlock your organization's true potential. Dive into the Analytics Hub now and soar to new heights!
NetSuite 2025.2 Release Notes - This document summarizes the changes to NetSuite between 2025.2 and the previous release.
To help you get the most out of your 2025.2 Release Preview account, review the topics outlined in the 2025.2 Release Preview Guide.
SuiteWorld October 6 - 9, 2025: Agenda Builder is live!

Read on for the latest updates including:
• Agenda Builder launch
• SuiteWorld On Air registration
• New NetSuite Prompt Studio Contest
• And more!

Check out this thread to learn more!

How to consider inbound Shipments for Supply Planning

Good day everyone. We have a need that feels like a gap in NetSuite's Supply Planning. I was hoping you all could tell me I'm missing something.

As you know (or, as far as I know), when preforming Supply Planning the Gross Requirements screen, and subsequently the Order Item Screen, consider the items on Purchase Orders ONLY. Specifically, the Expected Receipt Date informs Supply Planning for the arrival of the items. What we would like, is that Supply Planning considers the Expected Arrival Date of Inbound Shipments as well. Is this possible?

The use case is this: We may order 10 pieces to be delivered to us on the 6/1. Due to manufacturing issues, our supplier may only be able to get us 5 pieces on 6/1, with the remaining 5 Pieces planned to arrive 7/1. Currently, we split the PO line to 5 on 6/1 and 5 on 7/1 so Supply Planning is correct at the next analysis. This creates a large amount of PO maintenance.

Howdy, Stranger!

Log In

To view full details, sign in.