Work Order 1 has 40 units of Item A
- Each Operation has many Inspections associated with it.
- They required 100% inspection
- As in each item is required to get inspected before it moves from one operation to another
- NS can ONLY support 100% inspection on Lot and Serialized items and this lot controlled
- If the routing has 4 work stations and each station requires inspections
- I process Unit #1 and complete it with a WO Completion, the inspection request shows up in the queue to execute for the 1st operation
- Once I process Unit #1 inspection it will move to the 2nd operation to be processed
- Once I complete Unit #1 on the 2nd operation via a completion it appears NS is not generating an inspection request for unit#1 for the 2nd operation, as would be expected