HI Gurus, SuiteProjects….. please advise we are looking to work with employee work calendars and resource allocation. We have many projects/project task ongoing… Please can someone clarify if this statement means that when a user adds holiday/makes changes they need to go through each project with resources assigned to them and 'edit' one by one. I am unsure if I am reading right. If this is the case, could we look at some customisation to get this update itself. We are trying to get things as automated as possible so to expect someone to go through and manually update each project task would be painful.
NetSuite says…….Important: If you change a saved work calendar, the changes are reflected only in newly created projects or projects you edit and save.
It was also suggested that instead of using work calendars to reference non-working days, we may want to set up a dummy project named 'unallocated time' and here enter resource holidays/out of office/busy time. https://suiteanswers.custhelp.com/app/answers/detail/a_id/63869 I really am unsure which method is best and works with the resource allocation grid. Thank you in advance.