Has anybody ever dealt with how to handle billing customer when a portion of the services are funded through credits received by AWS under a Strategic Collaboration agreement and the delta is to be funded by the customer? We are dealing with invoicing through Jobs in Netsuite.
- The issue here is that using the Professional Services module in Netsuite, we have some limitations when it comes to billing this. I’d be interested to know how others are handling this, especially where there is a situation of a time and materials proof of concept (POC) engagement.
- Example: $40,000 estimate for a POC with AWS funding $20,000 through credits and the customer covering the rest, but based on actual hours.
- In Netsuite we need to do hours x rate = billed amount for T&M so as we incur hours, we can only invoice so much and therefore first need to capture $20,000 to AWS since that is fixed
- We don’t necessarily know the amount we’ll end up billing the customer so we need to wait to use up the $20,000 worth of hours
- We currently separate this into 2 jobs in Netsuite to be able to handle this, but this doesn’t seem like the best way or a scalable approach