Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Update your Profile with your Support type to get your Support Type badge.
Expand your NetSuite knowledge by joining our Ask A Guru Live sessions. RSVP on this event now.
Don't miss out on our Question of the Week! You only have until tomorrow, June 12, 2025, 2PM ET to comment your answers and earn rewards! Click here for more details.
Uncover the power of data with the Analytics Hub —your ultimate guide to mastering NetSuite Saved Searches and Reports. Simplify the complex and unlock your organization's true potential. Dive into the Analytics Hub now and soar to new heights!
SuiteWorld 2025 registration is officially OPEN
SuiteWorld is the largest annual gathering of the NetSuite community! It will be held in Las Vegas on October 6-9, 2025. Our customers and partners look forward to SuiteWorld every year as a place to hear the latest from NetSuite, get hands-on learning, and connect with each other. Register now!
SuiteWorld is the largest annual gathering of the NetSuite community! It will be held in Las Vegas on October 6-9, 2025. Our customers and partners look forward to SuiteWorld every year as a place to hear the latest from NetSuite, get hands-on learning, and connect with each other. Register now!
Starting June 1st, 2025, you may notice that our regular e-Fix releases are being referred to as ‘Minor Releases’. It’s still the same release schedule, with a different name. (Link can be found here)
Adjust Work Order Planned Start Date
Hi There
There is a scenario as follows:
There is a released work order for 100 qty of a good.
20 qty is produced and completed using a work order completion.
The remaining 80 qty will be produced at a future date at the request of the customer.
WIP and routing is in use as well as the manufacturing task scheduler.
How can the planned start date of the work order be pushed out into the future?
Is this something that can be modified with a script?
thanks
Tagged:
0