Hello,
We are evaluating Manufacturing Mobile for shop floor data collection and want to capture actual labor against Work Order Operations.
We have a Work Center (for example, a Spray Booth) that is staffed by a crew of five operators who perform the operation simultaneously. The Work Center is configured with five Labor Resources.
Our requirement is to record labor in a crew-based manner rather than having each individual operator separately clock in to the same Work Order Operation.
For example:
- A single lead operator or supervisor starts the operation in Manufacturing Mobile.
- If the operation runs for 1 hour, we want NetSuite to record 5 total labor hours (5 resources × 1 hour) against the Work Order Operation.
Is there a way in Manufacturing Mobile or Work Order Management to:
- Clock into a Work Order Operation at the Work Center level, and
- Automatically calculate actual labor hours based on the number of assigned Labor Resources,
without requiring each employee or resource to individually clock in?
If this is not supported natively, are there recommended approaches (such as Work Center configuration, labor multipliers, or customizations) to achieve crew-based labor reporting?
Thank you.