Here's a use case, one work order needs 20 motors on Monday. The open purchase order covers all 20, but its expected receipt date is Wednesday. Quantity on order alone will not tell you whether the build can start on time.
In NetSuite, review the motor item at the build location: quantity on hand, quantity committed, and quantity on order. Check the purchase order’s expected receipt date against the work order start date. If your team uses Supply 360, go to Reports > Supply 360 > Supply 360, filter to that location and date range, and open Shortages by Work Order. The short quantity, supply source, and first receipt date show whether the gap is stock, timing, or both.
If you use Demand Planning, compare the item’s demand plan with the supply plan’s suggested order dates and check the lead time used for replenishment. Note which input changed so purchasing and production can adjust the plan before the next run.