While at SuiteWorld, a customer asked me for help with a manufacturing issue they were having trouble with.
Their process was to release all work orders for the week on Monday, giving their production area full visibility of what was planned. Each work orders was dated for the day on which it was to be performed. So a list of those work orders might look like this:
WO# | Production Start Date |
|---|
1099 | Mon 11/30/26 |
1206 | Mon 11/30/26 |
1139 | Tue 12/1/26 |
1181 | Wed 12/2/26 |
1237 | Wed 12/2/26 |
1300 | Thu 12/3/26 |
1340 | Fri 12/4/26 |
Using typical commitment settings, releasing the work order commits the components immediately, regardless of the work order’s date. This lead to two problems:
- In some cases, components will arrive “just in time”, either the day before or day of the work order. Meaning that on Monday, the components for a Thursday work order would be back ordered and the work orders would indicate insufficient quantities to build. The back order is real at the moment of release (Monday) but not necessarily on the date of build (Thursday). This creates a kind of “false positive”, making it harder to understand where there are real supply issues.
- The second problem is a little tougher to explain. Imagine we have the list of work orders above: components needed for a Friday work order are committed on Monday. On Tuesday, we get a “rush” job for Wednesday production. Because the work orders for Thursday and Friday are already released, the components needed are already committed to them – which can prevent commitment of goods to the new Wednesday order if your component inventory is tight.
Fundamentally, what’s needed is a way to “release” work orders without committing components, then “release” them at a later time with commitment.
There are different ways to make this happen. In future replies to this post over the next few weeks, I’ll give you some details about each option. If you're interested, you can bookmark this post to keep an eye on it.
In the meantime if you've got some methods or ideas you've already tried, we'd be interested to hear about them, along with any pros/cons and lessons learned.