AE: POs from projects
Hi folks,
We are implementing Project Management module and happy to be able to create POs from projects. We have around 15 projects running simultaneously per year.
I have 2 doubts and wondering someone could shade a light:
1) Is there a way to link PO to tasks, instead of the whole project?
As far as we could understand, using the CUSTOMER field at line level of PO we are able to create the link. But this link is against the projects not the task.
2) Is there a way to group some POs of the same vendor, to get better performance either price and work wise of the procurement team ?