How to get Reschedule in messages to help identify items that need to be expeditied
We are using MRP Demand Planning and having trouble getting the RESCHEDULE IN Action Messages.
System is driving the right planned purchase orders for the right quantities but the due dates for the PO's is based on the item lead time. We are hoping to use the RESCHEDULE IN Action messages to identify which existing PO's need to be rescheduled in to satisfy the demand plan.
We have tried setting the RESCHEDULE DAYS value from 0 to 90
We have tried setting the RESCHEDULE HORIZON value as blank, 30, 60, 90, and 180 days
Looking for any advice regarding what is critical to set up for the RESCHEDULE DAYS Action messages to work