Join us for complimentary one-day events around the world and step into a future fueled by AI and limitless potential. Explore new breakthroughs, sharpen your skills, and connect with experts who are shaping what’s next. Experience bold keynotes, interactive learning, and connections that span the global NetSuite community. Discover what's next at SuiteConnect Tour 2026.
NetSuite has launched SuiteSuccess Wholesale Distribution Edition, in Japan. Please join us the webinar on February 12 that introduces NetSuite solution with demos and case studies for Wholesale Industry.
Register Now
Project summary tasks after all children/work tasks are deleted
It is possible to create the following multi-level project WBS, so long as each of the summary tasks is entered as a Milestone rather than Task.
Once a work task is added to a summary task, the summary task and all of its parents are no longer marked as milestones.
The Work 1.1.1 task can be changed to have Summary 1.2 as its parent.
However, after doing that, I cannot create a new work task that has Summary 1.1 as its parent.
The appears to be caused by Summary 1.1 no longer being a milestone AND not having any children tasks. It also still has the last computed value for Planned Work in the record. As a work-around, Summary 1.1 was changed back to milestone by editing it and saving it after setting the Planned Work field to zero and clicking OK at the prompt.