Work Order Expected Duration
Hi,
I'm hoping someone can help clear up/explain how NetSuite calculates the expected duration of a work order. Using the finite scheduling tool and the preview schedule feature, it shows the below work order's duration to be 632.18 hours. The work order quantity is 56, setup time is 153 min and run time is 47.04 min. If anyone knows the formula for this or could direct me to where this field is defined, it would be greatly appreciated.