Hi All
would need to understand how to solve the following issue.
Item X, assembled in location A, which needs item Y which is assembled in location B (external supplier) and which needs item Z which is assembled in location C (another external supplier) and which needs item K.
Item K is purchased and delivered to location A, then shipped to C.
Item Z, when completed, is shipped from Location C to Location A.
When Item Z is received in C, it is shipped to Location B.
When Location B receives Z, can produce Y and when it's done, can be shipped to Location A… that can produce X.
the way we set up the mrp, the only transactions that are suggested to me are:
- work order to produce X in Location A
- transfer order to transfer Y from B to A
- work order to produce Y in Location B
Can you tell me if there are any solutions?