Material Requirements Planning = T, Supply Planning Workbench > On Order does not show any value
Greetings, I see this Suite Answer, but this is talking about if the expected receipt date is after the repository refresh, I have a date of 8.11 as expected receipt date. I also created a PO in SB to Test out the theory that it might not be showing because the date is in past, but on order doesn't show for past or the future in.
how do I see the Quantity on Order on the Planning work bench screen?
Edit : When I re ran the workbench it picked up the future on order, but what happens to the past one?