Hello,
We are looking for feedback and user experience regarding the use of Planned Work vs. Estimated Work in NetSuite.
Our goal is to plan project resources in a detailed way by leveraging resource allocations at the task level. To do this we have unchecked the planned work feature
We have observed the following impacts:
- Project scheduling is manual. NetSuite shows dependencies but does not prevent dependency violations. It makes sense.
- "Schedule as Late as Possible" no longer seems to be available.
- Task start and end dates are calculated automatically, taking into account resource allocations and approved timesheets. This can lead to unexpected recalculations of task end dates.
- Estimated Cost is no longer calculated automatically. If not entered manually, it is no longer possible to account for timesheets.
Question: Is the task-level resource allocation mode fully supported and viable in NetSuite?