Hello,
We are having an issue with MRP. We keep getting duplicate Work Orders for several items. This doesn't appear to be happening on POs, only WOs. For example, qty 150 for item X on a work order for DEC 29, and then another qty 150 for item X on DEC 31. Why wouldn't this be qty 300 on DEC 29 if both are really needed?
For additional context, when looking at the pegging for both of these orders, the same three demand plans are the initiators.