Hi,
We are encountering an error when attempting to edit the Quantity (header) on certain Work Orders, even though this functionality has worked for us previously.
Earlier today, we successfully edited the quantity on Work Order 1 without any issues. However, when attempting to make the same change on Work Order 2, the system returned the following error:
“It is not possible to modify quantity when Component Yield is used on selected Bill of Materials, instead you can modify BoM Quantity.”
At first glance, both work orders appear to be set up identically:
- Same assembly item
- Same component structure
- BOM Revisions in use
- No intentional configuration changes were made between the two attempts
Because there were no known changes on our end between editing the two work orders, it is unclear why one work order allows the quantity to be edited while the other does not.
However, NetSuite allows us to update the BOM Qty Column, but that doesn't affect the Header Qty.
The Assembly Item has enabled 'Use Component Yielding'.
All components are inventory type.
Component Yielding on WO ranges 98% - 100% on both Workorders.
Can you help us understand:
- What conditions would cause NetSuite to allow quantity edits on one work order but restrict them on another?
Any clarification on the underlying cause or guidance on how to consistently manage this would be appreciated.
WO1: Successfully updated header qty.
WO2: Unable to edit header qty.
Regards,