Task/Close Manager
Summary
Task/Close ManagerContent
I have been investigating using Task/Close Manager as a replacement for HFM tasklists but it seems to have the following disadvantages:
- For the progress tracking to work you seem to have to create a task per input location. That is you cannot have a task Enter Movements you need Enter Movements Entity 10, Enter Movements Entity 20, Enter Movements Entity 30. This seems impractical if you have tens of locations.
- You do not seem to be able to change the order of tasks. That is if you want to insert a new task inbetween existing tasks it seems to be impossible. This makes it hard to guide users through tasks in a logical orders.
0