The allocation wasn't generated because there are no summarized amounts for the source projects.

edited Jul 30, 2020 10:17PM in Project Management 7 comments

Summary

The allocation wasn't generated because there are no summarized amounts for the source projects.

Content

Allocations failing with error:

The allocation wasn't generated because there are no summarized amounts for the source projects.

There is cost on the project, and accounting is in final mode.

I have already run the 'Update Project Performance Data' program, and Maintain Project Performance Data multiple times.

Any help, much appreciated.